Interior Improvements for a 140K SF warehouse fitout consisting of (2) office areas (1 area at 1,500 SF, 1 area at 3,700 SF). Office fitout work includes GWB partitions, wall and base cabinets/ countertops, acoustical ceilings, floor finishes (Carpet, LVT, VCT), window treatments. Bathroom finishes include wall and floor tile, toilet partitions, accessories and plumbing fixtures. MEP work includes RTU’s, ductwork, air distribution, fire sprinkler, lighting and power distribution/ fire alarm.
Project Milestone Dates:
– Project Walk-Thru: Wednesday 09/20/2023 at 2 PM. Address: 390 Spectrum Drive, Suite 100, Knightdale, NC
– RFI’s Due: 4 PM Thursday 09/21/2023
– GC Award Date: 10/04/2023
– Start of Construction: 10/13/2023
– Finish Construction: 02/02/2024